CHANNEL TUNNEL – EUROSCAN
PROJECT (1992)
28%
0%
Programme Overrun
Note: costs are converted at the 1992 Purchasing Power Parity
Architects liability
insurance prevents value
engineering;
Process
complexity
Contractor’s engineering
capability means value
engineering the norm
Strengths/weaknesses
Approximate Bill of
Quantity at Stage H; Full
JCT 80
Lump sum after stage D;
bespoke contract
Procurement
8
4
Site management Staff
equal
equal
Contract Programme
15%
8-9%
Contractor Cost Increase
£4,947,375
£4,502,178
Total Acquisition Cost
£4,482,375
£4,178,652
Contractor Out-tum cost
£3,897,000
£3,852,754
Contractor Tender Price
£465,000
£323,525
Design costs
BRITISH
PERFORMANCE
FRENCH
PERFORMANCE
PERFORMANCE INDICATOR
Source: Bartlett School
Of Graduate Studies; UCL
Contact: Graham Winch